Projects consisted of the installation of rooftop mounted solar panels and equipment as well as interconnecting them into SCE electrical grid. Work included installing Sunpower modules, wiring to combiner boxes, wiring of DC power to inverters at various enclosure locations, and wiring 12 KV AC power to switch gear and transformer for distribution back to SCE’s power grid. Work also involved constructing multiple equipment enclosures to house all the various components. Masonry enclosure was plastered with reveals to match existing building. EIFS conduit chase were also constructed.
The RDC 2 project consisted of (5,928) 2 MW panels, the RDC 4 project consisted of (15,680) of 5 MW panels, and the RDC 5 project consisted of (15,900) of 5 MW panels.